Dalekovod-Projekt has signed four new contracts with the Swedish transmission system operator Svenska kraftnät for the design of 400 kV transmission lines in Sweden, with a total length of nearly 600 km. The projects, with a total value of approximately EUR 30 million, will be delivered in partnership with Tyréns, with Dalekovod-Projekt acting as the lead partner. These large-scale infrastructure projects include feasibility studies, conceptual and detailed design, technical support during construction, and preparation of as-built documentation. Projects: - Stora Luleälven – design of two new 400 kV transmission lines (10 km + 24 km). The preparation of design documentation is planned until December 2028, while project completion is expected in 2033. - Hall–Hedenlunda – a new 400 kV transmission line with a total length of 77 km. The preparation of design documentation is planned until July 2030, with project completion expected by 2034. - Njutånger–Mehedeby – two partially parallel 400 kV transmission lines, each approximately 150 km long. The preparation of design documentation is planned until March 2029, with project completion expected in April 2034. - Skåne Syd – three new 400 kV transmission lines (17 km + 70 km + 75 km). The preparation of design documentation is planned until March 2034, while project completion is expected in the period from 2036 to 2038. These projects further strengthen the position of Dalekovod-Projekt and the Dalekovod Group in the Scandinavian market and represent a continuation of successful cooperation with Svenska kraftnät in the development of key energy infrastructure. At the same time, Dalekovod-Projekt’s strong presence in the Scandinavian market enables continuous and stable company growth, while the newly awarded projects will support the further expansion of its engineering team.