Projects Currently Actual

Project in Albania

The works investor on the project for the construction of the 400kV transmission line Tirana-Podgorica is KESH-OST (operator of the carrier system) from Albania and Elektroprivreda Montenegro, with the contractor being Dalekovod d.d. The project is contracted as a turn key solution.

The technically demanding project consists of an aerial double OHL 400kV line with a length of 76.14km, and a single air section 400kV line with a length of 80.80km. Besides the transmission line, this project includes the construction of a 400kV conductor field in the existing transformer station 400/210kV Elbasan 2, and two 400kV conductor fields in the transformer station 400/220kV Podgorica 2.

The deadline for completion of works in 24 months starting from the date of the advance payment.

Project Technical Specifications:
Length of transmission line: double OHL – 76.14km
Single line system – 80.80km
Double line – twin system pylons
Single line – standard pylons
Voltage level: 400 kV
Bundle conductor ACSR 3x2x490/65mm2
Insulation: glass capped insulators
Two protective lines – OPGW
Columns: steel-lattice
Columns: self-supporting - twin system Barrel shaped on the Tirana Vaau Dejes section
- single system shape "Y" on the section Vau Dejes - Podgorica