that is a part of the future 420 kV transmission line Nea-Jarpstromen (Sweden).
Despite problems and Investor’s delay with switching off of the existing feeder that enabled a continuation and finalization of works, owning to which Statnett extended the construction deadline till September 2009, Dalekovod finished all the works at the beginning of August 2009 to satisfaction of Statnett with no serious occupational injury which is the priority for the company Statnett during the process of carrying out construction works.